Estimate Activity Durations is the process of estimating the number of work periods to complete indivities with estimated resources . The tools and technques is not including ( ) .

  • Aexpert judgment
  • Banalogous estimating
  • Crequirements traceability matrix
  • Dthree-point estimating
参考答案: C