微信刷题,考证常用
  • 所属考试信息系统项目管理师试题库
  • 试题题型【单项选择题】
试题内容
You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as ( ) .
  • A.Ahead of schedule
  • B.Behind schedule
  • C.On schedule
  • D.Having not enough information provided
信息系统项目管理师在线题库
  • 参考答案:B
  • 解题思路:你是一个项目经理。你目前负责的项目预算是50万元,工期是6周。到目前为止,你已经花费了26万工程款,完成了预算中28万的工作量。根据你之前制定的进度计划,到目前为止,你应该花费30万元工程款。根据这些描述,你的工程目前____________。